Building
Status
Ready Date
     Machines
Interviewed
Remaining
Abercrombie Lab
In Progress
Apr 15-Jun 4, 07
85(A & B)
148(A & B), 40(C)
Allen Center
N/A
Jul 30, 07
-
321
Anderson Hall
Migration Complete
Jun 21, 06
-
-
Autry Court
In Progress
May 10, 07
51
12
Baker College
N/A
Aug 17, 07
-
250
Baker College Masters House
N/A
-
-
3
Baker Institute
Migration Complete
Jul 18, 06
-
-
Bio Lab (Anderson)
N/A
Jun 5, 07
82
111
Brown College & Wellness
Migration Complete
Oct 11, 06
-
-
Brown College Masters House
N/A
-
-
3
Central Kitchen (Hicks)
N/A
-
-
7
Cohen House
In Progress
Jul 31, 07
-
9
Continuing Studies
Migration Complete
Nov 10, 06
-
-
Dell Butcher Hall
In Progress
Jun 11, 07
90
78
Duncan Hall - North
In Progress
Mar 28, 07
297
320
Duncan Hall - South
In Progress
Mar 28, 07
297
320
Facilities and Engineering
In Progress
May 11, 07
175
43
Fondren Library (4th and 5th Floors)
In Progress
Apr 6, 07
24
3
George R. Brown Hall
In Progress
Jan 19, 07
363
17
Graduate Apartments
In Progress
Jul 20, 07
-
10
Greenbriar
In Progress
Ju1 15, 07
-
122
Hamman Hall
Migration Complete
Oct 23, 06
-
-
Hanszen College
Migration Complete
Aug 17, 06
-
-
Hanszen College Masters
N/A
-
-
2
Herman Brown Hall
Migration Complete
Oct 10, 06
-
-
Herring Hall
Migration Complete
Dec 8, 06
-
-
Herzstein Hall
Migration Complete
Feb 1, 07
-
-
Humanities
Migration Complete
Dec 22, 06
-
-
IBC Building
Migration Complete
Nov 2, 06
93
3
Jones College
Migration Complete
Aug 17, 06
-
-
Jones College Masters House
N/A
-
-
2
Jones School (McNair Hall)
In Progress
Apr 6-Jun 15, 07
-
215
Keck Hall
In Progress
Jul 30, 07
4
185
Keith-Wiess Lab
In Progress
Oct 1, 07
-
138
Library Service Center
In Progress
Jul 1, 07
-
7
Lovett College
Migration Complete
Aug 17, 06
-
-
Lovett College Masters House
N/A
-
-
2
Lovett Hall
N/A
Jul 15, 07
95
131
Martel College
Migration Complete
Aug 17, 06
-
-
Martel College Masters House
N/A
-
-
2
Mechanical Engineering (Cox)
N/A
Aug 1, 07
1
50
Mechanical Laboratory
In Progress
Dec 12, 06
1
50
Media Center
In Progress
Nov 10, 06
-
-
Mudd
In Progress
Apr 10, 06
-
-
O'Connor House
In Progress
Jul 20, 07
1
34
Police Station (Annex)
In Progress
May 8, 07
66
7
President's House (remote)
N/A
Jul 16, 07
-
2
Rayzor Hall
In Progress
Dec 17, 06
-
-
Reckling Park
Migration Complete
Feb 19, 07
-
-
Rice Stadium
N/A
Jul 4, 07
85
18
RMC (Ley Student Center)
Migration Complete
Sep 11, 06
104
0
Ryon Lab
In Progress
Apr 10, 07
45
20
Sewall Hall
N/A
Jul 23, 07
-
151
Shepherd (Alice Pratt Brown)
Migration Complete
Oct 9, 06
-
-
Sid Richardson College
Migration Complete
Aug 17, 06
-
-
Sid Richardson Masters House
N/A
May 30, 07
-
2
South Servery
Migration Complete
Aug 17, 07
-
-
Space Science
N/A
Jun 1, 07
120
122
Wiess College
Migration Complete
Aug 17, 06
-
-
Wiess College Masters House
N/A
-
-
2
Will Rice College
Migration Complete
Aug 17, 06
-
-
Will Rice College Masters
N/A
-
-
2
 
 
Start
Complete
Building
Status
Interviews
Migration