Section 4: Annual Reporting
A. Not later than [date] of each year, the Program shall prepare
and forward to each of the Parties a report on the Program's activities for the preceding
12 month period, and a projection of the Program's activities for the next 12 month
period.
1. The Annual Report shall include for the preceding 12 month period
the following: the revenues and expenditures of the Program, an accounting of all
mitigation credits created and sold, a description of the monitoring and maintenance
activities at mitigation sites, and the performance of mitigation sites.
2. The Annual Report shall include a description of the work to be
performed during the next
12 month period at individual mitigation bank sites, including work
previously approved by ACE which will create mitigation credits, as well as work to
monitor and remediate existing mitigation bank sites.
B. As part of the Annual Report, the Program may include conceptual
plans for mitigation work at new mitigation bank sites. No work at those sites will be
performed until the conceptual plan is approved by ACE pursuant to section 2.B above.
C. The Annual Report also may include proposed changes to any of the
policies, standards, criteria, guidelines or functional assessment procedures approved by
this Agreement and governing the Program's activities, as well as proposed changes to the
sites which qualify as mitigation bank sites, or development sites for which mitigation
credits can be purchased. None of these changes shall be implemented until approved by
ACE.
Section 5: Miscellaneous
A. This Agreement may be amended only by a written amendment signed by
all parties to the Agreement. Changes to any of the policies, standards, criteria,
guidelines or functional assessment procedures criteria which govern the selection of
mitigation or development sites, or the creation or use of mitigation credits, may be
approved by agreement between Eugene and ACE.
B. This Agreement shall continue in effect until all mitigation credits
created by the mitigation bank sites have been sold and the Program has completed all
monitoring and maintenance functions required at all mitigation bank sites.
C. Definitions (???)
|