Camassia Newsletter, March 1994
Page: 1 | 2 | 3 |
4 | 5 |
6 | 7 |
8
Study Looks at Restoring Lower Amazon Creek Wetland
The U.S. Army Corps of Engineers is studying the possibility of
restoring a section of Amazon Creek to its historic flood plain and
surrounding wetland.
The purpose of the Amazon Creek restoration study is to restore
environmental resources, including fish and wildlife habitat lost as a
result of flood-control projects, while continuing to provide
flood-control benefits.
The Amazon Creek study area ( XXX see map, page 3) includes the lower
Amazon Creek from Danebo Avenue downstream to Green Hill Road, as well as
the section of the "A" Channel from the diversion structure to
Green Hill Road and the section of the "A3" Channel from Danebo
Avenue to the "A" Channel. This area was chosen because it
offers the highest wetland restoration potential.
The study looks at several options:
- Remove sections of the existing channel levee along the Amazon and
"A" and "A3" channels, retain a low-flow channel to
direct dry-season flows, widen the channel, and reduce bank slopes as
shown in the cross section to the left. Wetland vegetation would be
established in the channel bottom, while maintenance and clearing
requirements would be reduced. These changes would allow wetlands adjacent
to the channel to flood periodically.
- Modify the levees. Under this alternative, the existing levees would
either be breached with culverts or notched" by removing a small
section to allow additional water into wetland areas. This option is less
expensive than levee removal and allows easy control of water to adjacent
wetlands. However, this option would not allow the area to return to a
natural appearing and functioning condition.
- Restore and enhance the existing wetland system. This could be
done by restoring a complex system of braided stream and swale features,
re-establishing the mound and swale topography naturally associated with
lower Amazon Creek basin, developing shallow ponds, and planting native
wetland vegetation with an emphasis on establishing habitat for rare and
threatened plant species.
- Build water quality retention ponds. Two retention ponds are being
considered as a part of the overall landscape design. The ponds would
pretreat water flows before release into natural wetland areas.
- Include the Amazon Creek bicycle path in the overall design of the project
as appropriate. The bike path would follow along the north side of Amazon
Creek from west Eugene to Fern Ridge Lake.
An interagency advisory committee has reviewed the draft study, and the
Corps has published its findings and recommendations in a report titled
Amazon Creek: Environmental Restoration and Reconnaissance Study.
In the next phase, the Army Corps of Engineers and the City of Eugene will
consider the feasibility of proceeding with various options.
A Delicate Balance
The Amazon Creek wetland restoration study is an effort by the U.S. Army
Corps of Engineers to integrate multiple objectives into its planning
process.
In the early 1940s, the Corps built Fern Ridge Reservoir in response to
flooding problems in the Willamette Valley. In 1959, the Corps completed a
flood control project along Amazon Creek consisting of approximately eight
miles of concrete and earthen channels and a 3.8-mile-long diversion canal
emptying into Fern Ridge Reservoir.
The channelization of the Amazon Creek system has attected the natural
environment. Designed to provide flood control, these projects reduced the
water supply to natural wetlands, diminished the regular flooding that
provided water and nutrients to the wetlands, and drained adjacent wetland
areas. Furthermore, increased flood security allowed for a more intensive
level of agricultural and industrial development to occur in the area. The
net result has been the loss ot signiticant wetlands and ash forest that
provided habitat for many endangered and threatened plant species.
|
Page: 1 | 2 | 3 |
4 | 5 |
6 | 7 |
8

|