IV. CONCERNS & QUESTIONS RAISED ABOUT THE WEST EUGENE WETLANDS DRAFT PLAN
A. |
Regional Permit
|
|
1. |
Need a clear explanation of the regional permit,
(Oral: Bodine, 4-8-92, p.3)
|
|
RESPONSE:
Section 404 of the Clean Water Act, passed by Congress in
1972, assigns the Army Corps of Engineers (COE) the
responsibility to administer a regulatory permit program for
activities involving discharge of fill material in wetlands.
The permit program seeks to ensure that the nation's
wetlands are used in the best interest of the public. Any
person, firm, or agency wanting to fill or dredge a wetland
must first obtain a permit from the COE.
Section 404(e) of the Clean Water Act authorizes the COE
to issue general permits on a regional basis for activities
involving discharge of fill material in wetland sites. A
general "regional" permit is a way for COE to apply its
regulatory program to an area identified in a wetlands
management plan. The regional permit would authorize all
activities that are consistent with the plan and would
likely place most of the responsibility for processing
individual permit applications with the local jurisdiction
that administers the plan.
|
|
2. |
Vote against the "regional permit" L-COG is requesting,
(E. Brown, S).
|
|
RESPONSE:
We are continuing to communicate with COE (and Division
of State Lands) about the best way to treat the west Eugene
Wetland Plan once it is adopted locally. The goal is to add
certainty and predictability to the west Eugene region and
to streamline the wetland permitting process. We believe
shifting responsibility to the local jurisdiction, through a
general "regional" permit, will increase certainty and save
time and resources for both COE and private property
owners.
|
|
3. |
With the regional permit, there will be no appeal for an
individual caught up in this maze, (J. Lorenz, X).
|
|
RESPONSE:
A regional permit would help streamline the wetland
permitting process by consolidating existing federal, state,
and local permit requirements at the local level. The local
operating procedures will include provisions for appeal of
local wetland permit decisions. The procedures also will
acknowledge the authority of the Army Corps of Engineers to
review and comment on local permit decisions, provide
assistance, and verify compliance with permit criteria.
|
|
|
4.
|
How much do we really know about it from sources outside
of the local hired staff? (J. Lorenz, X).
|
|
|
Information about general "regional" permits is readily
available from the Army Corps of Engineers. A COE
representative participated in the recent workshop and
provided written information about the federal regulatory
permit program.
|
| | Index for Summary of Comments and Staff
Responses
|
|
B.
|
Wetlands Definition
The following three comments raise questions about
wetlands definitions and the federal and state wetlands
manuals which establish the criteria and methodologies for
field determinations, delineations and assessments of
wetlands functions and values. A common response is provided
for all three comments.
|
|
|
1.
|
Need current federal and state definition of "wetland",
(Oral: B. Bodine, 4-8-92, p. 3).
|
|
|
2.
|
The delineation method used is undergoing scrutiny. How
do these affect the need for the Plan?, (Oral: J. Getten,
4-8-92, p. 2).
|
|
|
3.
|
Definitions keep changing (J. Lorenz, X).
|
|
|
RESPONSE:
This staff response addresses comments 1-3 above:
The U.S. Army Corps of Engineers and the Oregon Division
of State Lands, the two wetlands regulatory agencies, and
EPA which has a role in the Corps permitting process, all
use the following, common definition of wetlands:
"Those areas that are inundated or saturated by surface
or groundwater at a frequency and duration sufficient to
support, and that under normal circumstances do support, a
prevalence of vegetation typically adapted for life in
saturated soil conditions. Wetlands generally include
swamps, marshes, bogs, and similar areas." (Executive Order
11990, 1977 and ORS 196.800 (16)).
There are two versions of the "Wetland Manual" officially
in use; a third version of the Manual was proposed in the
Federal Register (Vol. 56, No. 157) on August 14, 1991. The
1991 version underwent a 60 day public comment period that
was extended for another 60 days, expiring in February 1992.
To date, no official action has been taken on the proposed
1991 Manual changes by any federal or state agency - it has
no official status. The Corps was directed by Congress (1992
Energy and Water Development Appropriations Act - printed as
H.R. 2427 on July 10, 1991) to discontinue to approve
permitting decisions based on the 1989 Manual. In a
memorandum for division and district commanders from Corps
Counsel, dated 8-23-92, the Corps began mailing permitting
decisions based on its previous 1987 Manual (U.S. Army Corps
of Engineers Wetlands Research Program, Technical Report
Y-87-1). However, the Corps can approve some wetland
decisions where inventories or wetland plans were underway
at the time Congress provided the above direction (8-23-92
memorandum, p.1). Oregon has chosen to remain with the 1989
Manual through reference in an internal policy signed by the
Director of DSL. The draft Wetlands Plan uses the 1989
Manual because it sets the highest standard that the Plan
must meet. The Objectives of the draft Plan state that the
Plan should meet federal and state laws and regulations (p.
1). To address the changing definitions issue, the draft
Plan contains a new Recommended Action, #7.11 which states:
"Once agreement is reached by state and federal agencies
on a uniform method for defining and determining wetlands,
the Plan's inventory will be re-evaluated and Plan
amendments may result". (Planning Commission recommended
amendments to the draft Plan, p. 25, memorandum to the
Council and Board dated 4-24-92).
The differences between the 1987 and 1989 Manuals affect
all three wetland parameters, hydrology, soils, and
vegetation.
There are at least seven bills introduced in the U.S.
House of Representatives that would amend the wetland
provisions of the federal Clean Water Act. It is not
projected that any new Wetland Manual or wetland amendments
will occur before 1993. The wetland issues are likely to be
the most controversial of all amendments being proposed in
the Clean Water Act. It is anticipated that there will be
changes to wetlands definitions, criteria, and regulatory
approaches sometime during the next 24 months. The history
of wetlands definitions and the Manual indicate that both
have changed numerous times since the Clean Water Act was
originally adopted in 1972. Given the controversy over
wetlands, it is likely that definitions and the Manual will
continue to undergo change during the next two decades.
|
| | Index for Summary of Comments and Staff
Responses
|
|
C.
|
Takings Issue
|
|
|
1.
|
Article 14 of the U.S. Constitution states that no
private property shall be taken without just compensation
and due process of Law, (Oral: F. Brown, 4-8-92, p. 3) and
What effect will the Lucas case before the U.S. Supreme
Court have on wetlands? (Oral: Delores Bales, 4-8-92, p.
3),
|
|
|
2.
|
Property rights are being taken without compensation,
(M.Hudspeth, W).
|
|
|
3.
|
The plan invades private property and causes added
controls on land, (oral: L. Germyn, 4-8-92; M).
|
| | Index for Summary of Comments and Staff
Responses
|
|
D.
|
Other Legal Issues
Wetlands delineation can't be used to devalue property
and then use federal funds to buy wetlands at deflated
values caused by a federal regulatory program, Florida Rock
Industries, Inc. vs. United States, 791 F2d 893, 905 (Fed
Cir. 1986), (Oral: A. Johnson, 4-8-92; O).
RESPONSE:
This response covers items C, Taking Issue, and D, Other
Legal Issues.
There are two parts to the response to these questions.
The first has to do with the policies included in the WEWSAS
which apply to the Secondary Study Area where the commentors
own property. In the Secondary Area, within the proposed
acquisition area, property owners have the option to make
voluntary sales to the Bureau of Land Management at fair
market values. No forced sales are proposed, authorized or
encouraged by the Plan. The BLM can use condemnation only
when specifically authorized by Congress to do so, and for
this project, no such authorization has been given.
Therefore, the acquisition program proposed in the Secondary
Study Area would not diminish the economic use of private
property.
The only policy which would restrict uses on private
property within the Secondary Study Area is policy 3.14,
which would restrict some uses along stream channels and on
hillsides. (See discussion of policy 3.14, Section 4, VI
H.).
The second response to these questions about the taking
of property comes as a brief explanation of how a "taking"
is determined. It is well established that if a taking is
found to have occurred, the proper measure of just
compensation is the property's fair market value at the time
of the taking. The taking would ordinarily be deemed to have
occurred at the time of the governmental action resulting in
elimination of all economically viable use of the property.
It would ordinarily be necessary to determine the fair
market value of the property both before and after the
governmental action that resulted in a reduction of economic
use, to determine whether the diminution of value was
sufficient to constitute a taking.
The "Lucas case" referred to is Lucas v. South
Carolina Costal Council, 404 S.E. 2d 895 (1990), cert.
granted, No. 91-453 (U.S. Sup. Ct., 1992). Oral argument has
been heard in the U.S. Supreme Court. Although a decision
could be issued at any time, most commentators expect a
decision near the end of the current term in June.
Lucas is a regulatory takings case, in which
landowner Lucas claims that application of South Carolina's
"1988 Beachfront Management Act" to his two parcels of
beachfront property constitutes a compensable taking because
the regulation eliminated all economically viable use of his
property. Lucas did not challenge the validity of the
regulatory legislation, which was based in significant part
on fmdings by the legislature that regulation of beachfront
development was necessary to~prevent great public harm, and
to protect a valuable public resource. Lucas argued that he
is entitled to compensation for elimination of all
economically viable use of his property, regardless of the
legislative basis for the regulation. The South Carolina
Supreme Court rejected that argument, based upon a line of
cases holding that no taking occurs when regulation is
applied to prevent serious public harm or nuisance.
The U.S. Supreme Court's decision in the case definitely
could have a significant effect on the cost of governmental
regulation of private property. The Lucas case has a
number of factors and issues at work, and it is practically
impossible to guess the precise issues the court will choose
to address, much less the positions the court will take. In
addition, the composition of the court has changed
significantly since the last important regulatory takings
case was issued in 1987. It is quite possible, though
unlikely, that the court will not reach the takings issue
because of some procedural technicalities that have arisen
at the state level. The court might adopt the argument of
landowner Lucas that governmental regulation resulting in
sufficient diminution of value constitutes a compensable
taking, regardless of the purpose of the regulation. The
court might preserve the "harm-nuisance prevention"
exception to takings, but limit application of the rule to
classic nuisances rather than any activity the legislature
determines to be detrimental. There are other positions the
court could take, as well. It does not appear likely that
the court will move away from the requirement that
government action result in elimination of all economically
viable use of an identifiable segment of property in order
to establish a compensable regulatory taking.
|
|
|
2.
|
Affidavits
|
|
|
Affidavits were received from approximately 90
individuals who own property within or near the secondary
study area. All of the affidavits are identical. The text of
the affidavits make two statements concerning the draft
WEWSAS:
"... the implementation of the study in its present form
has the potential to cause severe land use restrictions and
would constitute a taking of my private property rights
without just compensation. Whether my property is designated
to be protected wetland, wetland to be developed or
considered to be a potential contributing wetland factor,
the effect will be to impair the use of my property right."
"The incorrect designation of all or part of my property
as wetlands and the resulting impairment of my property
right will substantially harm the property's present and
future value and will also cause direct economic harm to
me."
RESPONSE:
The draft study does not designate any property in the
secondary area as wetlands, nor does it designate any
property as "protected wetlands", "wetlands to be
developed", or as "a potential contributing wetland factor".
The study only identifies areas that are eligible for
voluntary sale to the Bureau of Land Management for use in
the proposed mitigation program.
|
| | Index for Summary of Comments and Staff
Responses
|
|
E.
|
Property Values
|
|
|
1.
|
If owners are "persuaded" to sell property for lump sum
payment, they would suffer serious tax implications, (Oral:
M. Powell, 4-8-92, p. 3; G).
|
|
|
RESPONSE:
The reference to "serious tax implications" presumably
refers to taxation of the gain realized from sale of the
property. A "lump sum" payment of the purchase price
received in the year of sale would result in taxation of the
entire gain in that year. However, if the purchase price was
paid in installments, taxation of the gain would be, m
essence, pro-rated over the period of installments. To
evaluate the tax implications of one approach over the
other, it would be necessary to know the specific details of
the seller's tax situation. A willing seller, however, can
request installment payments to spread the gain from the
sale over more than one year.
|
|
|
2.
|
Speculation caused by the Plan has inflated land values;
is this wise use of federal Land & Water Conservation
Funds? (Oral: Bodine, 48-92).
|
|
|
RESPONSE:
Land and Water Conservation Funds are used by the U.S.
Government to purchase and protect natural resource areas of
national interest. By appropriating almost $2 million to the
Eugene District of BLM in 1991, the U.S. Congress and the
President gave a strong indication that these wetlands in
west Eugene were of national interest. There is nothing in
the land & Water Conservation Fund Act which declares
that federal interests are restricted to remote, pristine
natural areas. In fact, there is growing interest at the
federal level in dealing with more urban natural situations
(U.S. Department of the Interior, Fish & Wildlife,
Wetlands Action Plan, 1990, "Urban Wetlands Initiative", and
National Park Service, "Rivers and Trails Program"). In
lobbying for the L&WCF, the City of Eugene pointed out
to the Oregon Congressional delegation that the wetlands
"problems" in west Eugene were caused by federal wetlands
and endangered plant laws. The use of L&WCF to purchase
areas of concern were linked directly to federal programs
and interests through Congressional and Presidential
actions.
|
|
|
3.
|
If property is designated as wetlands, it can't be
divided off for children, (Oral: M. Powell, 4-8-92, p. 3;
G).
|
|
|
RESPONSE:
Within the secondary area, WEWSAS does not force or even
persuade landowners to sell property, and no Plan
designation of "wetland" is made. Division of land among
heirs would require legal land division conforming to
existing zoning regulations. In the case of agricultural
land, 40-acre parcels are the minimum size. Information in
WEWSAS concerning the secondary area does not change the
zoning on the property, nor does it create an overlay zone.
Provided the minimum lot size is met, potential for land
division is unaffected by WEWSAS. Acquisition of a wetland
by a government agency would also have to conform to minimum
parcel standards for creation, unless a lot size variance
was approved.
|
|
|
4.
|
Is legal for the Lane County tax assessor to have already
recognized the wetland boundaries as jurisdictional and to
have already reassessed and devalued properties? (Oral:
Lorenz, 4-8-92, p. 4; E; T. Stewart, Y).
|
|
|
RESPONSE:
The Eugene/Springfield Metro Plan designated a large
portion of the west Eugene area for industrial use. After
the Metro Plan was adopted, local governments invested in
infrastructure to support industrial uses (for example, $12
million in sewers and roads). Property owners' and
investor's expectations for economic development in this
area were raised. Expectations of benefits arising from
ownership became premised primarily on industrial and
commercial development, and property values adjusted
accordingly.
The West Eugene Wetlands Special Study Area, through the
work of consultants has delineated wetlands in the primary
study area. Much of the acreage delineated as wetlands were
in the industrially designated area of the Metro Plan.
In order to help wetland owners who had hopes of
developing their land for industrial uses, the lane County
Tax Assessor chose to re-evaluate land in the primary study
area to see what influence new federal wetland regulations
had on assessed values. Few sales of wetlands were available
in the affected area, which established a need for the
Assessor to utilize alternate sources of value information.
The Tax Assessor looked at listings, reviewed professional
opinions and sales outside the Eugene-Springfield area to
gauge the impact on property values of wetlands.
The Tax Assessor did not recognize wetland delineations
as jurisdictional boundaries. After scientific research of
specific properties in the west Eugene area, the Tax
Assessor looked for opportunities to help wetland owners
reassess the value of their land, since it had been expected
to be utilized for industrial purposes.
The valuation issue created by new federal wetland
regulations and the need for the Assessor's office to bring
the reappraisal program for Lane County back into compliance
with state statutes coincided. The need to deal with both
issues presented a problem since resources are limited in
the County Assessor's office.
Faced with resource limitations on the one hand and the
~goal of uniform assessment on the other, a range of
processes for implementing a program to equalize values in
the west Eugene areas were discussed. The proposals extended
across a spectrum from delaying correction of wetland values
until the regular reappraisal cycle to doing a complete
reappraisal in 1990. Delaying reappraisal would relieve
concerns about resource limitations and assure compliance
with state mandated goals, although it would not meet the
need for uniform assessment of properties in the west Eugene
area. Undertaking a complete reappraisal of the west Eugene
area properties would correct the assessment inequities, but
resource limitations would jeopardize meeting the state
mandated goals which would lead to revenue withholding.
The Lane County Tax Assessor's chose a compromise
solution and to equalize land values in the west Eugene in
phases. The first phase occurred in 1990 and involved
reviewing wetland properties and adjusting values of the
wetland portion of individual properties. The second phase
took place from 1990-1992 and involves monitoring the
effects of wetland on property values and making the
necessary adjustments where and when indicated. By the end
of 1992 phase three will be completed. This phase includes
full consideration given to wetlands as well as all other
factors to be considered in reassessing the property
values.
|
|
|
5.
|
Losses due to wetlands will affect some owners more than
others; it is too bad that the burden of protecting the
watershed cannot be shared more equally, (Oral: J. Selliken,
4-8-92, p. 7).
|
|
|
RESPONSE:
In the absence of a wetland plan like WEWSAS, the burden
for wetland protection and mitigation generally falls
entirely upon the private property owner who happens to have
regulated wetlands on his/her property. The WEWSAS
Technical Report discusses possible ways to distribute
this burden among a broader constituency including local,
state, and federal governments, non-profit conservation
organizations and other sources. The draft WEWSAS Plan
recommends financing that includes federal funds for
acquisition and local stormwater user fees as well as
property owner contributions. This will ease the burden on
property owners.
|
|
|
6.
|
WEWSAS will devalue land by adding restrictions, (S, E.
Brown; UU, G. Brown; YY, D. & D. Bales; EEE, S. Bales;
FFF, J. Mathey; GGG, W. Moodie).
|
|
|
7.
|
Don't let "middle man" get the money when people are
"forced" to sell, (W-3, M. Hudspeth).
|
|
|
8.
|
This is a "land grab" in disguise; owners want guarantees
that it isn't, (W-3, M. Hudspeth).
|
|
|
9.
|
Landowners will benefit by having their land designated a
wetland because they will not be threatened by suburban
sprawl. (Oral: F. Gillespie, 4-8-92, p. 6).
|
|
|
10.
|
How will acquisition of land affect adjacent land values?
(W-10, W. Moodie).
|
|
|
11.
|
What economic effect will this plan have on the entire
city and county?, (W-2, Anonymous).
|
|
|
12.
|
Pay fair market value for property you need to acquire.
(W-8, Anonymous).
|
|
|
13.
|
Is the acquisition program only for willing sellers in
the secondary area, or is it the same in the primary area?
(W-10, W. Moodie).
|
|
|
14.
|
If these lands are designated wetlands, what is land
worth if there are no buyers? (Oral: W. Welch, 4-8-92, p.
6).
|
|
|
15.
|
Purchase of wetlands will adversely affect real estate
transactions. The owner of a five-acre parcel had a sale
fall through because of the plan - the buyer wanted to build
a barn. (U, I. & I. Whitt; X, J. Lorenz).
|
|
|
16.
|
Can I continue to farm my property? (W-3, M.
Hudspeth).
|
|
|
17.
|
See response below.
|
|
|
18.
|
If there aren't enough willing sellers, will property be
taken in order to implement the plan? (III, M.
Hudspeth).
|
|
|
19.
|
How much tax revenue will be lost if the proposed
acquisition plan is completed? Will this loss cause taxes to
rise? (III, M. Hudspeth).
|
|
|
Concerns 6-19 express issues related to property values.
A common staff response to these points follows concern #19.
Also, see the information provided by BLM in handouts
presented as part of the 5/2/92 workshop attached as part of
the results of the workshop (a separate section of this
document).
RESPONSE:
The Plan should not decrease property values for three
reasons: 1) Wetlands have not been determined; 2) It has not
caused any rezoning or Rural Comprehensive Plan
redesignation; and 3) It has not placed additional
restrictions on uses now allowed (for example, normal farm
or forest practices). Furthermore, the Plan should improve
values because it creates a market for lands meeting certain
criteria. Also, there is likely to be a market for wetlands
restoration. That market and need should increase the land
values. When willing sellers negotiate with BLM and a fair
market appraisal is conducted, the market for wetlands
restoration should be taken into account by the appraiser.
Property owners should always be cautious of individuals
who might try to use the Plan, wetlands law, or other
reasons to frighten owners by claims of devaluation. Until
the first transactions are conducted, few people understand
the value of potential wetland restoration sites or the
value of a wetland.
The BLM's Land & Water Conservation Funds would be
used to purchase land or conservation easements only from
willing sellers. The acquisition process involves an
independent appraisal to determine fair market value of the
land. Even then, the owner must be agreeable to the offer
sale price before a land transaction can occur. A direct
action from the U.S. Congress would be required before BLM
could use condemnation powers to acquire land.
No takings result when there are no additional
regulations placed on the land and implementing the draft
Plan relies on acquisition from willing sellers at a fair
market value.
When a parcel or portion of a parcel is purchased by BLM,
it is intended that the purchase would include enough land
so a buffer can be formed between adjacent land and the
restored or enhanced wetland. Buffers have been an effective
way of mitigating the impacts from normal farming and
forestry practices in most instances. However, the trend in
the federal Clean Water Act has been to impose stricter and
stricter standards over time on water pollution. There may
be a future law or regulation which places additional
controls on non-point sources (surface runoff of
stormwater), but those regulations would take place with or
without the draft Wetland Plan.
Under the Plan, property owners sell to another private
party. There is nothing in the draft Plan which says you are
required to sell only to BLM.
The plan does two things:
|
|
|
a.
|
It shows areas that have hydric or wetland type soils
that were once wetlands on Concept Map No. 4. These areas
are lands that may be suitable for wetlands restoration in
the future, and;
|
|
|
b.
|
It allows a willing owner to sell areas which are
suitable for restoration to the Bureau of Land Management or
a non-profit conservation organization. This restoration
could then become part of the west Eugene Wetland Plan's
mitigation program.
|
|
|
There is no intent to force land sales. BLM's brochure,
"West Eugene Wetlands Project", 5-1-92 states "In 1991,
Congress appropriated funds to the Eugene District of the
Bureau of land Management (BLM) to implement the acquisition
phase of the project. BLM procedures allow for acquisition
of private land from willing sellers." (emphasis
added). If there are not enough willing sellers, there will
not be a condemnation program to force the mitigation bank
concept. The requirement for mitigation of impact still
falls primarily on the individual property owner. The bank
concept is an attempt to pool community resources to solve a
community problem in a way that is a fair as possible to all
affected parties.
Until the first land acquisition transactions are
completed, it is difficult to estimate the land value to be
purchased. However, the Lane County tax assessor has
conducted a mass reappraisal of wetland areas in the primary
study area to $800 to $1,000 per acre. If all 1,070 acres
slated for protection or restoration were purchased by BLM,
the loss in tax revenue to the affected city, county and
districts would be approximately $26,750 assuming a tax rate
of $25.00 per $1,000 assessment rate. (Assuming 1,070 acres
X $1,000 per acre assessed value X $25.00 per thousand tax
rate = $26,750 of property tax revenues). The acreage
figure, the assessed value and rate are all subject to
change. The City's Lower Amazon Flood study conducted by
OTAK consultants in 1990 estimated costs of approximately
$10,000,000 to provide additional flood detention basins and
channel improvements to meet future urban growth needs in
the Amazon drainage basin. To the degree that the Wetland
Plan can offset the needs for those flood control public
facility improvements, the $26,750 loss in tax revenue due
to BU~ land purchase can be offset.
The loss in revenues would affect several taxing units of
government. In tax code area 4-01, for example, Eugene
School District, lane Educational Service District, lane
Community College, and lane County would be affected by loss
of annual property tax revenues resulting from federal
acquisition. Based on 1991-92 information from the
assessor's office, the respective levies of those four
taxing governments fisted above were $71.6 million, $7.2
million, $20.6 million, and $12.7 million. The respective
impact of spreading the loss of $26,750 among other tax
payers represents a minuscule percent increase per $1,000 of
assessed value.
|
|
|
17.
|
Will land values be changed by interim protection
measures? (VV, M. & R. Ringsdorf).
|
|
|
RESPONSE:
No. The implementation measures are expected to be
applied to protected wetlands one they are acquired (for
example, redesignation and rezoned as natural resource
areas). The land transaction between a willing seller and
BU~ would have already taken place with an independent
appraisal and fair market value transaction.
|
| | Index for Summary of Comments and Staff
Responses
|
|
F.
|
The Plan
|
|
|
1.
|
How does the WEWSAS Plan offer policies and strategies
which are better than those currently in place?, (Oral:
48-92, C. Fisher, p. 3; D. Henning, p. 6; F, C. Fisher; D,
T. Stewart; X, J. Lorenz).
|
|
|
RESPONSE:
There are two primary reasons why local jurisdictions are
beginning to adopt local wetland policies and strategies: 1)
current federal and state programs have not been effective
at implementing wetland protection law, and 2) existing
state and federal wetland permitting processes have created
uncertainty in implementing local economic development
objectives. There are many reasons why current state and
federal wetland programs are ineffective, most are the
result of fragmented programs that have no common goal and
no coherent strategy. As a result, they have floundered,
providing inadequate protection for the resource, and often
fail to respond to legitimate development needs. With the
inherent difficulties of implementing national policy at the
local, urban level, many cities and urban counties have
turned to the local comprehensive wetland planning process.
The Draft WEWSAS Plan is one example. When adopted, it will
provide certainty as to the location of existing wetlands
resources (federal/state policies do not), a measure as to
the relative value of the wetlands, a plan for how they are
to be managed (protected versus impacted), a program to
direct mitigation efforts where the degree of success and
value will be maximized, a program for maintaining the
resources,a financing plan for implementation, and a local
wetland permitting process. These policies, therefore, offer
greater certainty that wetland resources will be protected,
and that economic development will proceed on some of the
wetlands that have been found to be lower value.
|
|
|
2.
|
Will this plan work? (Anonymous, W-2).
|
|
|
RESPONSE:
As with any plan, the success of WEWSAS will depend on
many factors. Perhaps the most important factor is the
community's commitment to make the Plan work. With the
partnerships that have been developed between local, state,
and federal agencies, and the $1.9 million appropriated by
the U.S. Congress for wetland acquisition in west Eugene,
the Plan has gotten off to a good start start. It is now up
to the community to make it work.
|
|
|
3.
|
Were other alternatives considered? (NN10, A. Wobbe).
|
|
|
RESPONSE:
Yes. Chapter VII, Alternatives Analysis, WEWSAS
Technical Report, April, 1991, contains both the
required State Goal 5 analysis for the natural resources,
(Environmental, Social, Energy, Economic {ESEE}), and seven
wetland management alternatives. The management alternatives
were presented to the public at WEWSAS Workshop 5, at which
the workshop participants were surveyed as to their
preference. The survey results were used in developing the
staff recommended draft plan.
|
|
|
4.
|
Multiple objectives approach is beyond scope of this
plan, (X,J. Lorenz).
|
|
|
RESPONSE:
Wetland resource benefits are often described in terms of
their functions and values, of which there are many,
including: flood control, water quality, wildlife habitat,
recreation, education, and economic value. Most of these
values relate to a service or responsibility that the City
of Eugene currently provides to the community, either as a
local choice such as recreation, or in meeting federal
mandates such as flood control and stormwater water quality
enhancement. In developing the objectives of the wetland
management plan, public participants encouraged a plan that
would not only meet the minimum requirements of federal and
state wetland law, but a plan that recognizes and achieves
the economic benefits of combining multiple community
objectives through a consolidated, comprehensive
program.
|
|
|
5.
|
Mitigation bank is a convenient way to insure jobs for
L-CO(3, (X,J. Lorenz).
|
|
|
RESPONSE:
This comment is an opinion. How the mitigation bank will
be established and who manages it has yet to be determined.
L-COG may or may not be involved in management of the
mitigation program.
|
|
|
6.
|
Does the plan affect all properties in the secondary
area? (VV, M. & R. Ringsdorf).
|
|
|
RESPONSE:
No. the Plan only identifies areas along the primary
water features in the Amazon Basin that may be suitable for
wetland restoration and mitigation credit. The suitability
of these areas is based on the presence of hydric soils,
proximity to waterways, within the 100 year flood plain,
compatibility to existing uses, and through a willing
participant or seller.
|
|
|
7.
|
Are goals & objectives most important part of plan?
(VV, M. & R. Ringsdorf).
|
|
|
RESPONSE:
The Plan contains goals, policies, and recommended
actions. The goals provides overall guidance while the
policies provide specific direction to attain the goals. The
recommended actions carry out or implement the policies. The
goals and policies are the cornerstones of the Plan, while
the recommended actions are advisory, subject to
modification.
|
|
|
8.
|
Who has overall responsibility for Plan since it pertains
to more than one jurisdiction?, (VV,M. & R.
Ringsdorf).
|
|
|
RESPONSE:
Responsibility for implementing the Plan will require a
joint management agreement that will likely involve the City
of Eugene, lane County, and the Bureau of land management.
The City Public Works and Development and Planning will have
major roles inside the City and the urban growth boundary.
The County would implement the Wetland Plan on rural lands
within the primary study area and within the Rural
Comprehensive Plan jurisdiction in the secondary study area.
BLM~ would implement the Plan on any federally owned lands
according to process required in the land and Water
Conservation Fund Act and the Federal land Policy and
management Act, Public law 94-579, October 21,1976.
|
|
|
9.
|
Plan designates all areas from city limits to Fern Ridge
Reservoir as wetlands, (AA, C. & A. Fairchild; UU, G.
Brown; 55, 5. Barr).
|
|
|
RESPONSE:
The Plan does not designate any areas in the
secondary study area as wetlands. What the Plan does in the
rural area is described in staff response to Iv. F. 6.
above.
|
|
|
10.
|
Plan doesn't state what total costs will be, (BBB, J.
Tapp).
|
|
|
RESPONSE:
The Plan identifies most of the cost factors for its
implementation, including land acquisition for protection
and mitigation, construction for mitigation and restoration,
operations and maintenance, and other capital projects. The
Plan does not contain cost information for administration of
the wetland bank or regulatory process requirements.
|
|
|
11.
|
Removes 3,500 acres from private ownership, (RR, S. Keep;
BBB, I. Tapp).
|
|
|
RESPONSE:
The Plan provides for the protection of 1,070 acres, and
the impact of 360 wetland acres for future development
according to zoning regulations. The impact of wetland
resources requires mitigation, or the replacement of "lost"
wetland acres. According to the recommended 1'Mitigation
Replacement Schedule" contained in the Plan, a worst case
scenario would result in the need for 653 mitigation acres.
The total effect of the Plan, therefore, is 1,623 acres
(1,017 plus 653). The additional 1,877 acres (3500 minus
1,623) are recommended to account for "non-willing sellers"
and to provide additional mitigation capacity in the event
the greater Eugene community faces other mitigation needs,
such as the expansion of the Eugene Airport, Short Mountain
I~dfill, and other public and private projects. The Plan
does not mandate the removal of 3,500 acres from private
ownership, rather it offers a variety of methods to achieve
its minimum and optimum goals, including the possibility of
acquiring all of the acres into public ownership through a
willing seller basis. In order for this to occur, however,
funding must be secured and willing sellers available.
Because of this uncertainty and the desire for flexibility,
private mitigation is an option available through the Plan.
Therefore, it is more likely that a combination of private
and public wetland ownership will occur.
|
|
|
12.
|
Plan has hidden agenda, (X,J. Lorenz).
|
|
|
RESPONSE:
This comment is an opinion. The Plan's goals and policies
are fully disclosed in the March 1991, Draft Plan, as
recommended for amendment by the Planning Commissions.
|
|
|
13.
|
Plan tries to separate land from private property owners
by having a non-profit or public agency acquire private
property, (X,J. Lorenz).
|
|
|
RESPONSE:
This comment is an opinion. There are no requirements in
the Plan to force a transfer of ownership to a public or
private non-profit agency.
|
|
|
14.
|
Why must all other existing plans & policies be
amended to conform with WEWSAS? WEWSAS should be amended to
conform with existing plans, (X,J. Lorenz).
|
|
|
RESPONSE:
Whenever a refinement plan to the Metropolitan Area
General Plan is developed, it must be accompanied with
findings of consistency with the Metropolitan Plan. If
inconsistencies are identified, there are two remedies: 1)
propose amendments to the Metropolitan Plan to make the two
consistent or change the draft refinement plan to remove the
sections or provisions which are deemed to be inconsistent
with the Metropolitan Plan. In developing the WEWSAS, it was
recommended to amend the other plans and policies to make
them consistent with WEWSAS, because WEWSAS contains the
latest facts and findings regarding natural resources in the
affected area.
|
|
|
15.
|
Hasn't recommended action 3.12 already been done?, (X,J.
Lorenz).
|
|
|
RESPONSE:
Yes. Lane County has amended its code to reflect Senate
Bill 3 from the 1989 Oregon Legislative session. As per OURS
215 and Lane Code, wetlands enhancement, restoration or
creation is an allowed use in agriculturally zoned
areas.
|
|
|
16.
|
If WEWSAS is approved before natural resources study is
acted on, what happens if the referenced protection measures
in NRSS get changed through that process? (X,J. Lorenz).
|
|
|
RESPONSE:
There is a joint staff team developing the implementing
measures which -will be used to implement the WEWSAS and
NRSS recommendations. The two plans are similar in their
recommendations. Coordination between these documents and
the three agencies will continue during the public review
and adoption process. It would be desirable to end up with
one, consistent set of implementing measures for both plans.
That is the staff goal which is consistent with direction
form the Planning Commissions and elected officials on many
other joint projects in this metropolitan region. Of course,
there will be amendments made to the staff proposed draft
measures before they are finally adopted.
|
|
|
17.
|
How does plan minimize economic hardship on property
owners? (X,J. Lorenz).
|
|
|
RESPONSE:
For property owners that have jurisdictional wetlands on
their property recommended for protection, the Plan provides
a funding source to purchase the wetlands on a willing
seller basis, relieving them of an otherwise uneconomic
condition. For property owners required to mitigate for
wetland losses due to fill activities, the Plan provides a
preplanned, preconstructed mitigation program where
mitigation obligations are purchased through credits,
providing them certainty and saving them time and money.
|
|
|
18.
|
Prairie grasslands never dominated in Willamette Valley,
(X,J. Lorenz).
|
|
|
RESPONSE:
The extent of grasslands in the Willamette Valley at the
time the first settlers arrived is well documented by the
maps and notes of the original land surveys conducted by the
General Land Office in the 1850s. These maps show that
roughly 750,000 to 1,000,000 acres of grasslands were found
in the Willamette Valley at that time. More specifically,
these sources also show that much of west Eugene was
occupied by grasslands at the time of settlement.
|
|
|
19.
|
Prairie grasslands is a sub~limax plant community that
can not sustain itself without human intervention, (X,J.
Lorenz).
|
|
|
RESPONSE:
The Willamette Valley grasslands were maintained by the
management practices of the native inhabitants for thousands
of years. Over that time, a "natural" balance was
established whereby a unique and diverse landscape,
supporting a variety of food plants, as well as a number of
endemic species, was supported and maintained. In this
context, the real issue is whether we, as a society, wish to
see a few small remnants of this landscape survive in the
future. In this modern age, no place on earth is without
human influences, whether they be direct or indirect. In
the case of the Willamette Valley, the choice is between
continuing human influences to perpetuate a few small
examples of an ecosystem that has been present in the valley
for thousands of years, or to allow other influences, human
and otherwise, to displace the last remnants of this
ecosystem.
|
|
|
20.
|
What does the greenway out to Fern Ridge Reservoir have
to do with the industrial land in the UGB? (X,J.
Lorenz).
|
|
|
RESPONSE:
The greenway is not the objective of this Plan, rather it
is a possible outcome of the overall objectives of the Plan
which are to meet wetland law requirements, provide greater
flood control capacity, improve water quality, and to
implement other aspects of the Eugene-Springfield Metro Plan
and the County Rural Plan, such as the Fern Ridge Bike
Trail. Compensating for wetland losses due to future
industrial development, such as Spectra-Physics, provides an
opportunity to replace wetland losses along the Amazon
Channel in the form of a greenway.
|
|
|
21.
|
Is the interconnected system the entire 65 square miles
that this plan affects?, (X, J. Lorenz).
|
|
|
RESPONSE:
The interconnected system includes the recommended
protected and restored wetlands, and the main water features
in the Amazon Basin, such as the Amazon Channel, A3 Channel,
A Channel, Willow Creek, Coyote Creek, and the headwater
streams in the south hills. The Plan envisions a 3,500 acre
restored wetland watershed, which is approximately 5.5
square miles.
|
|
|
22.
|
Goal 5.2, What watershed management principals? By whose
definition?, (X, J. Lorenz).
|
|
|
RESPONSE:
The intent of Goal 5.2 is to promote the development of
routine operations and maintenance practices that will
ensure the health and survival of protected wetlands. An
urban watershed is composed of many elements, including
uplands, riparian areas, wetlands, waterways and developed
surfaces. It is generally accepted that these elements
function as an integrated system and that disturbance to an
individual element has the potential to impact the other
parts of the system. Some examples of this are the effects
of removing vegetation from waterways on downstream wetlands
or the impact to receiving waters due to the development of
upland areas. Goal 5.2 proposes that operations and
maintenance practices advance the multiple objectives of the
WEWSAS Plan.
|
|
|
23.
|
Why were pages 47 through 50 eliminated? (X, J.
Lorenz).
|
|
|
RESPONSE:
Pages 47 through 50 were not eliminated from the Plan.
These pages have been revised and reformatted into a tabular
form in the Planning Commission' s recommended amendments to
the draft Plan. The information contained on these pages
remains the same.
|
|
24. |
Regarding recommended action 7.1: What is the purpose of having more restrictive
regulations? (X, J. Lorenz).
|
|
RESPONSE:
There is nothing in recommended action 7.1 that states local regulations for fill and
drainage in wetlands would be more restrictive than state or federal laws and regulations.
If local jurisdictions assume local wetland permitting authority, both the state and
federal agencies will require that local regulations be no less than those of higher
agencies.
|
|
25. |
Regarding recommended action 7.3: Did L-COG bother to contact the Fair Board to get
their input? (X, J. Lorenz).
|
|
RESPONSE:
The concrete lined section of the Amazon Channel does not border Fair Grounds property.
The City of Eugene has been in communication with the Fair Board about the effects and
recommendations of the draft Plan on the fairgrounds.
|
|
26. |
Since the Natural Resources Special Study has not been accepted yet, why is it part
of this plan? (X, J. Lorenz).
|
|
RESPONSE:
The techniques used to implement the WEWSAS and NRSS plans are expected to be similar.
There is no need to have separate implementation measures to carry out separate natural
resource directions. Where those natural resource plans have similar conclusions and
recommendations, the implementation measures should also be similar to avoid community
confusion and to promote easy administration of those measures.
|
|
27. |
Plan puts plants and swamps~ahead of people, (00, A. & P. Grenon; UU, G.
Brown).
|
|
RESPONSE:
The Plan proposes to balance the ecological needs of sensitive wetland habitat with the
economic and social needs of the community.
|
|
28. |
Are the proposed amendments from the planning commissions now part of the plan?
(III, M. Hudspeth).
|
|
RESPONSE:
No. The amendments are recommendations from the Planning Commissions to the elected
officials. The elected officials can elect to: 1) incorporate all or a portion of the
amendments, 2) not include the amendments, or 3) add to the amendments in their final
action.
|
| | Index for Summary of Comments and Staff
Responses
|
| G. |
Mitigation
|
|
1. |
The ratio concept on p. 30 is confusing; why does mitigation in advance of impacts
reduce the need for replacement unless success is known in short time period, (Oral: D.
Jones, league of Women Voters, 4-8-92, p. 4, B).
|
|
RESPONSE:
In an effort to clarify the mitigation concept, a revised schedule has been recommended
by the Planning Commissions which is contained in the recommended Planning Commission
amendment package. The revised schedule includes a definition for "advance of
impact," which requires the restoration effore to be in place, functioning, and
meeting the performance criteria set out in the plan at the end of the required monitoring
period. When mitigation occurs m advance of impact, a net gain in wetland functions and values results as no wetland losses will have occurred, providing successful
mitigation credits in the bank. The basis for mitigation ratios greater than one-to-one is
due to the uncertainty often associated with mitigation efforts. With successful
mitigation demonstrated prior to impact, the need to over compensate for expected wetland
losses (i.e., ratios greater than one-to-one) is reduced. Thus, the provision in the
mitigation section to reduce the ratio by .50 acres for advance of impact mitigation
credits.
|
|
2. |
Don't try to make something with wetlands that is not by trying to mess with Mother
Nature, (W,M. Hudspeth).
|
|
RESPONSE:
Wetland restoration and mitigation is a concept provided by federal and state law. The
chances of successful mitigation increase with a solid understanding of the goals and
objectives of the mitigation project, an understanding of the basic water, soils, and
vegetation requirements of the desired habitat, and an on-going monitoring and maintenance
program. There are examples in west Eugene where wetlands have been created even without
the proper planning (Danebo Pond). To increase the chances for successful mitigation
efforts, the West Eugene Plan targets historic wetland areas (i.e., areas with hydric
soils and adequate water conditions) as the preferred mitigation sites. In these areas,
wetland functions and values are likely to be restored with little effort, such as ceasing
the activity which causes the disturbance (i.e., farming activities such as plowing and
cropping).
|
|
3. |
Are there enough mitigation acres in the primary area?, (VV,M. & R. Ringsdorf).
|
|
RESPONSE:
Yes. However, the availability of these acres depends upon willing sellers. To insure
choice and availability, additional suitable acres are
desirable.
|
| | Index for Summary of Comments and Staff
Responses
|
| H. |
Funding
|
|
1. |
Given the uncertain current economic climate, the funding proposals may not be
realistic, (Oral: D. Jones, league of Women Voters, 4-8-92, p. 5;
B).
|
|
RESPONSE:
Securing long term funding for the West Eugene Wetlands program has been an on-going
component of the work program for the project. Several relationships with other
organizations are being established that ultimately should mitigate the community cost for
the program. The relationships currently include those with BLM, The Nature Conservancy,
and Oregon Department of Transportation. The establishment of a wetlands bank should be
self-supporting through investments by the development community and long term local management will likely be financed by stormwater user
fees.
Public Works staff have begun the process of developing a comprehensive stormwater
management plan of which wetlands management is an integral part due to wetlands water
quality and flood protection characteristics. Financing of the stormwater program will
include such sources as assessments, systems development charges, and storrnwater user
fees. It is likely the stormwater user fees will be a principal source of funding for the
overall program and will be based on impervious surface area. The financing mechanisms
will apply to those areas where the City's stormwater program has jurisdiction, that is,
within the city limits. These financing mechanisms will not apply to areas outside of the
city limits unless annexation occurs. The rural area is unaffected.
Given recent Environmental Protection Agency mandates regarding storrnwater quality,
alternative or expanded funding sources will have to be established. Even with the
uncertain economic climate, the community will need to address these pressing
environmental issues.
|
|
2. |
City should not buy and sell real estate, (MM, W. & P. Burgess).
|
|
RESPONSE:
The WEWSAS has recognized that the best way to preserve the highest quality wetlands in
the community is to purchase the property and place it under public ownership. If the
higher quality wetlands remained in private ownership, additional regulations and on-going
monitoring would likely be required to assure that the natural resources where not further
degraded.
The City may purchase land or utility easements necessary to make public facility
improvements or retain the ability to maintain those facilities, including transportation,
flood control, stormwater conveyance, and water quality.
The BLM will be purchasing the majority of the properties necessary to accomplish the
goals of the WEWSAS plan. If additional funds are necessary, other funding sources will
need to be secured and the City will then likely proceed with the purchases using the same
legal processes as BU~ for acquisition. Also, its anticipated that other governmental
agencies may be negotiating for wetland sites in the area to meet project related
mitigation requirements. The City does not plan to sell any property but will likely allow
development to buy into the wetland bank concept outlined in the plan.
|
|
3. |
All residents should bear cost of the wetlands problem, (JJ, Church of God, The
Eternal).
|
|
RESPONSE:
The WEWSAS will be funded by a variety of sources including Federal (BLM), volunteer
resources, non-profit organizations, wetland bank, systems development
charges (SDCs), assessments, and storm user fees. The storm sewer user fees will be collected
City wide and indirectly the Federal funds represent a broader participation by the
nation.
|
|
4. |
Can the community afford operations & maintenance of wetlands? (X,J. Lorenz;
VV, M. & R. Ringsdorf).
|
|
RESPONSE:
The community will not be expected to bear the burden of this cost alone. The
operations and maintenance will be performed by BLM, The Nature Conservancy, volunteer
groups, City staff, etc. A portion of the operations and maintenance will be a direct
result of maintaining storm conveyance and flood protection and improving the quality of
stormwater. Recent EPA mandates are requiring that communities of the size of Eugene
address stormwater quality and that natural methods are part of the solution. The
multipl~use objectives of the plan will allow for broader based support in the community
versus just focusing on wetlands preservation.
|
Table of Contents
Index for Summary of Comments and Staff
Responses
Next Page of This Report